82.7 million |
|
33,400 USD |
Summary | |
---|---|
|
€ 69.7 million |
|
€ 24.9 million (36% of total cost) |
|
€ 44.9 million (64% of total cost) |
|
€ 87.81 million |
|
€ 55.4 million |
|
€ 26.9 million |
|
€ 6.51 million |
Schools | |
|
1,000 |
|
5 with 8 classrooms each |
|
1,650 per school x 5 = 8,250 |
|
2,000 m2 per school x 5 = 10,000 m2 |
COST: | € 12.7 million, out of which: |
|
€ 1,300/m2 x 1,650 m2 x 5 schools = € 10.7 million |
|
€ 2.0 million |
TOTAL COST OF SCHOOLS: | € 12.7 million, out of which: |
|
€ 5.4 million |
|
€ 7.4 million |
INCOME: | € 7.0 million per year |
|
@ € 7,000 per student per year € 7,000 x 1,000 students = € 7.0 million per year |
RUNNING EXPENSES: | € 4.3 million, out of which: |
|
@ € 4,000 per teacher/staff person per month (two full time teacher/staff per classroom of 25 students) = 2 staff x 8 classrooms x 5 schools x € 4,000 x 12 months = € 3.8 million per year |
|
€ 0.5 million per year |
OPERATING SURPLUS: | € 2.7 million per year, out of which: |
|
Payment of € 7.4 million with 8% interest over 10 years to bond holders or bank = € 1.07 million per year |
|
20% of surplus after payment of financing = € 0.32 million per year |
|
€ 1.28 million per year |
Hospitals | |
|
6 with 600 beds total |
|
30,000 m2 |
|
30,000 m2 |
COST: | € 57.0 million, out of which: |
|
50 m2 x 600 beds x € 1,300/m2 = € 39.0 million |
|
€ 12.0 million |
|
€ 6.0 million |
TOTAL COST OF HOSPITALS: | € 57.0 million, out of which: |
|
€ 19.5 million |
|
€ 37.5 million |
INCOME: | € 80.81 million per year |
|
@ € 738 per bed per day and 50% occupancy. 300 beds x € 738 x 365 days = € 80.81 million per year |
RUNNING EXPENSES: | € 51.1 million |
OPERATING SURPLUS: | € 24.2 million per year, out of which: |
|
Payment of € 37.5 million with 8% interest over 10 years to bond holders or bank = € 5.44 million per year |
|
20% of surplus after payment of financing = € 3.8 million per year |
|
€ 15.0 million per year |